Day 2 and all is going to plan. Main structures are in and sealed, and studio diffusers are 2/3 in. I guess today will be the most impressive as the main structure is up and taking shape. Day 3 will be wire and pipes as the AC, AV, audio, network and electricity all gets plumbed in and tested. Then we’ll be fine tuning the acoustics of the main studio space. We don’t want it to be just dead space as we’re aiming to be able to control levels of spark for Foley and the occasional musical instrument. After tomorrow there’s one day build on Tuesday with the glass coming in, final AC, mez flooring then a day the following week when the doors get fixed. Hitting our 50m2 in 5 days target. Then we’ll party.